Almost everyone underestimates, and almost everyone believes they are the exception. The only way to find out is to write the estimate down before the work and the actual after it, enough times that the pattern stops being deniable.
How to use this tool
Before you start a task, log it with your honest estimate in hours. Not the time you wish it would take — the time you actually expect.
After you finish, come back and fill in the actual. Count only time spent on the task.
After five or six entries a personal ratio appears. After fifteen it is worth trusting.
Use the calibrator at the bottom to turn a fresh estimate into a realistic one.
The one rule that makes this work: never edit the estimate after the fact. The moment you adjust an estimate to match what happened, the log stops measuring anything and starts flattering you.
A ratio of 2.0 means the task took twice as long as you thought. A ratio of 1.0 means you called it exactly.
How this maps to Jira and similar trackers
Mapping between this tool and common tracker vocabulary
Here
Jira
What teams actually argue about
Estimate (hours)
Original Estimate
Whether to estimate in hours at all
Actual (hours)
Time Spent / worklog
Whether logging time is useful or surveillance
Your ratio
no direct equivalent
Most teams never compute this, which is why they keep missing
—
Story Points
Relative size, deliberately not hours
—
Velocity
Points completed per sprint — a team's empirical ratio in disguise
Story points exist largely because hour estimates are so unreliable. A team estimates relative size, measures how many points it actually finishes per sprint, and plans from that measured number instead of from anyone's optimism. Velocity is the team-scale version of what this tool computes for one person. It is also routinely misused as a productivity metric by managers, which is why engineers get twitchy about it.
Log a task
No entries yet.
Your log
Estimates and actuals. Fill in an actual by typing in its cell.
Date
Task
Type
Est.
Actual
Ratio
Actions
What your log says
By type of work
Median ratio per type of work. Types with fewer than three finished entries are marked as too few to trust.
Type
Finished
Median ratio
Reading
Log a few finished tasks and observations will appear here.
Calibrate a new estimate
Log some finished tasks first.
This multiplies your estimate by your own measured median. It is not a prediction — it is your track record applied to your optimism.
Reflect
Keep your work
This tool remembers your work in this browser on this device. Nothing is sent anywhere.