Planning forward from today tells you when you might finish. Planning backward from the deadline tells you when you have to start — which is the only one of those two numbers that can be wrong in a way that hurts.
How to use this tool
Enter the hard deadline. Not the date you would like to be done — the date something bad happens if you are not.
List the tasks with a duration in working days each. Duration is elapsed working days, not effort hours: a task that needs two hours of your time but three days of waiting for a machine is three days.
Under each task, tick what it depends on. That is what turns a list into a schedule.
Add a buffer. Ten to twenty per cent is a normal starting point; zero is a statement that nothing will go wrong.
Read the verdict. If the required start date is already behind you, the plan is not late yet — but it will be, and right now you can still do something about it.
Critical path is the longest dependent chain through the work. Every task on it has zero slack: delay one by a day and the whole project moves a day. Tasks off the critical path have float, which is why "I'm behind on my bit" means completely different things depending on which bit you have.
Weekends are skipped. Holidays, exam weeks and lab closures are not — subtract those yourself, or add them as a task.
How this maps to Jira and similar trackers
Mapping between this planner and common tracker vocabulary
Here
Jira / project tools
Note
Deadline
Version / fixVersion, or a milestone
The date the outside world cares about
Task duration
Duration in a Gantt view (Advanced Roadmaps, MS Project)
Not the same as an effort estimate
Depends on
"is blocked by" issue link
The link type most teams under-use
Critical path
Computed in roadmap tools; absent from a plain board
A Jira board deliberately hides this
Slack / float
No standard field
Usually lives in someone's head, badly
Sprint boards and critical-path planning answer different questions, which is why teams often run both. A board tells you what is moving this week. A backward plan tells you whether the whole thing lands. Agile teams sometimes treat dependency planning as a relic of waterfall — but hardware, fabrication, procurement and anything with a lead time do not care what your process is called. A part that ships in six weeks ships in six weeks.
The tasks
No tasks yet.
The verdict
Add tasks and a deadline.
The schedule
Latest start and finish for every task, working backwards from the deadline. Slack is how many working days a task can slip before the whole project does.
Task
Days
Depends on
Start by
Finish by
Slack
Path
Timeline
The bars above repeat the table visually. Solid bar is the task; the hatched extension is its slack.
What the plan says
Add a few tasks and observations will appear here.
Reflect